One option A risk response introduces a new risk. What should the project manager do? Identify, analyze, record, and manage the secondary risk Ignore it because the original response was approved Delete the original risk Treat the new risk as an issue even if it has not occurred Send vote A risk response introduces a new risk. What should the project manager do? #PMP_2026_practice_test #PMP_mock_exam #PMP_questions #project_management_certification #People_Process_Business_Environment #agile_hybrid_predictive